Chennai Metro Commences Phase I Trials

The Chennai Metro Rail Limited (CMRL) on Saturday, 26th December 2020, commenced the 9-km trial run between Washermanpet and Wimco Nagar Metro Station. The trial run of 9.051 km for the Diesel Locomotive vehicle was successful, according to Chennai Metro Officials.

This trial run will pave way for the CMRL’s plan for fully completing the entire Phase I extension works. The line from Washermanpet to Wimco Nagar is an extension of phase-1 corridor from Washermanpet to Airport via Annasalai with eight metro stations, namely Washermanpet, Toll Gate, Kaladipet, Thiruvottiyur, Thiruvottiyur Theradi, Thegaraya College, Tondiarpet and Wimco Nagar. Out of these, Thegaraya College and Tondiarpet are two underground stations.

“The Installation of various systems including Ballastless track, Overhead electrification, Signaling, Tunnel Ventilation, HVAC, Platform screen doors, Automatic fare collection (AFC) gates are currently underway in this stretch to achieve early commissioning,” a release from CMRL read.

The officials said the services are scheduled to be open for the public by end of January 2021.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.